UIC Hospital MEOP

About The Project

The UIC MEOP project included a partial replacement of a large medical building’s critical systems while the hospital remained in operation. The installation mandated blending legacy systems with a new design. CCC worked diligently with the building tenants to ensure existing mission-critical services were not interrupted.

Project Manager, Andrew Wagner, says of the project, “Creativity was the cornerstone of our success. We collaborated with the owner to maintain existing system operations active while changing them over to the new design. It was a complicated process that required true trade partners. The quality of their work, attention to detail, and willingness to come up with solutions for complicated problems paved our way to successful delivery.”

Details

Completion:

Fall 2017

Unique features:

Replacement of air handling units, temperature control system, electric, and piping